Upcoming ILSB projects
Spring break will be busy
We have several upcoming structural and operational events in the ILSB
Friday, March 17th:
Removal of the stainless steel sink in room 324C for modifications to accommodate our new autoclave. Remove sink, cap services and patch wall.
Removal and modification of framing panels above the vivarium cage washer
Monday, March 20th:
Drainage project along the south side of the building. Expect work to continue throughout the week
Electric boiler testing for the vivarium heat system exact date to be determined.
Wednesday – Thursday March 22nd – 23rd: (Pending confirmation)
Reverse Osmosis (RO) water loop sanitization, RO will be highly chlorinated and unusable until the 24th.
Saturday, March 25th:
3rd floor power outages for autoclave preparation, work involves access to room 324D and 324C.
Outage will affect the entire 3rd floor, labs, classrooms and offices, except for emergency power and lighting.
TBD
Plumbing work to accommodate new autoclave, work will be done in room 324C, 324D and 324-3 (Equipment hallway)
Thank you all for your attention