All,
The floors of the UMBC research labs are scheduled to be cleaned, stripped and rewaxed starting on the 4th floor, Monday evening August 1st. ABM will be starting on the 4th floor on the 1st, continue on to the 3rd floor on the evening of August 2nd and then complete the 2nd floor research labs on the 3rd. The ESL and main lobby will be completed the evening of the the 4th.
Shortly thereafter we will be coming back for the setting areas on each of the upper floors, schedule to be determined.
This project will concentrate on the wet lab areas only, we will not be working in either the procedure, shared services spaces nor tissue culture rooms. The crew asks that all supplies and or equipment on the floors of the wet labs be moved to a shelf or bench top before leaving the day assigned for cleaning.
I'll be walking the building with the supervisor the week prior to the work to color code areas off limits.
Please let me know that you've seen this message and please share it with anyone from your lab I may have missed.
Thank you!